A Project Manager is setting up the project's organization structure. They need to ensure that the Project Board members understand their responsibilities. Which TWO of the following are responsibilities of the Project Board? (Choose two.)

⚠ Common exam trap

Test-takers frequently confuse the strategic governance role of the Project Board with the operational responsibilities of the Project Manager and team, such as managing daily activities or creating products.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Approving the project initiation documentation

The Project Board is responsible for approving the project initiation documentation and authorizing project closure. These are key governance decisions that ensure the project remains aligned with business objectives and is formally closed. Day-to-day management, product creation, and work package assignment are delegated to the Project Manager and team.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Managing the day-to-day activities of the project team

    Why it's wrong here

    Managing day-to-day activities is the responsibility of the Project Manager, not the Project Board. The Project Board provides direction and makes key decisions, but delegates daily management to the Project Manager. Involving the Board in daily tasks would be inefficient and contrary to the principle of manage by exception.

  • ✓

    Approving the project initiation documentation

    Why this is correct

    The Project Board is accountable for the overall success of the project. Approving the project initiation documentation (PID) is a key decision at the end of the initiating a project process. This approval authorizes the Project Manager to proceed with the project. It ensures the Project Board has reviewed and accepted the project's baseline before committing resources.

  • ✓

    Authorizing the closure of the project

    Why this is correct

    The Project Board authorizes project closure after confirming that all products have been delivered and accepted, and that the project has met its objectives. This decision is made at the end of the closing a project process. It is a critical governance responsibility to ensure the project is formally closed and benefits are realized.

  • ✗

    Creating the project's products

    Why it's wrong here

    Creating products is typically the responsibility of the project team, under the direction of the Project Manager and Team Managers. The Project Board does not create products; they provide governance and strategic direction. Their role is to ensure the project delivers the required products, not to produce them.

  • ✗

    Assigning work packages to team members

    Why it's wrong here

    Assigning work packages is a Project Manager responsibility, often delegated to Team Managers. The Project Board focuses on higher-level decisions, such as approving plans and tolerances. They do not get involved in operational task allocation, which is part of the controlling a stage process managed by the Project Manager.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.