Courseiva
PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

A Project Manager is preparing to close a project. The Project Board has confirmed that the project's products have been handed over to the operational and maintenance environment. Which activity is part of the Closing a Project process?

⚠ Common exam trap

Many exam-takers confuse stage-level planning or initiation activities with project closure, when Closing a Project is specifically about confirming handover and evaluating the project against its Business Case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Producing the End Project Report and evaluating the project against its Business Case

Closing a Project involves confirming that all products have been handed over, evaluating the project against its Business Case, and producing the End Project Report. These activities ensure the Project Board can confirm that the project's objectives have been met and that there are no outstanding issues before authorising closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Authorising the next stage and updating the Project Plan with the latest actuals

    Why it's wrong here

    Authorising the next stage occurs during Managing a Stage Boundary, not Closing a Project. Updating the Project Plan with actuals is part of stage boundary and progress reporting activities. Closing a Project focuses on confirming handover, evaluating the project, and preparing the End Project Report.

  • ✓

    Producing the End Project Report and evaluating the project against its Business Case

    Why this is correct

    Closing a Project includes activities to confirm handover, evaluate the project against its Business Case, and produce the End Project Report. This report summarises performance against the project's objectives, benefits, and tolerances, providing the Project Board with the information needed to authorise project closure.

  • ✗

    Producing the Stage Plan for the final stage and updating the Risk Register

    Why it's wrong here

    Stage Plans are produced during Managing a Stage Boundary, not Closing a Project. While the Risk Register is reviewed and updated throughout the project, producing a Stage Plan for the final stage is not an activity of Closing a Project, which deals with project closure rather than stage planning.

  • ✗

    Creating the Project Initiation Documentation and securing Project Board approval

    Why it's wrong here

    Creating the Project Initiation Documentation occurs during Initiating a Project, where the Project Board approves the project's baseline. Closing a Project is the final process, concerned with confirming that the project has delivered its products and that the Business Case is satisfied or can be closed.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.