People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A project is running over time by 5% against the stage tolerance of 10%. The Project Manager expects this trend to continue. What should the Project Manager do?

⚠ Common exam trap

Many exam-takers confuse a deviation that is still within tolerance with one that is forecast to exceed tolerance, leading them to incorrectly choose the Exception Report option (B) when the correct action is to continue and report via the Highlight Report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Continue and report the deviation in the next Highlight Report

The project is within the stage tolerance of 10% (currently at 5% over time), and the Project Manager expects the trend to continue but has not yet exceeded the tolerance. According to PRINCE2, the Project Manager should continue managing the work within the agreed tolerance and report the deviation in the next Highlight Report, as this is the standard mechanism for communicating progress and forecast deviations that are still within tolerance. Raising an Exception Report is only required when a deviation is forecast to exceed the stage tolerance, which is not the case here.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue and report the deviation in the next Highlight Report

    Why this is correct

    The deviation is within tolerance, so the PM can manage it and report as normal.

  • Raise an Exception Report immediately

    Why it's wrong here

    An Exception Report is only needed when a tolerance is forecast to be exceeded.

  • Ask the Project Board for more time

    Why it's wrong here

    Not necessary as the tolerance is not breached.

  • Update the Business Case to reflect the delay

    Why it's wrong here

    The Business Case does not need updating for a minor delay within tolerance.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.