Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

A project is nearing the end of a stage, and the Project Manager is preparing for the End Stage Report. The Project Board has asked for assurance that the project remains viable and that the stage has delivered what was agreed. Which activity in the Managing a Stage Boundary process directly supports that assurance?

⚠ Common exam trap

The trap here is selecting the Board's authorisation decision as the activity, when the process activity is the Project Manager preparing the End Stage Report and updated Business Case that inform that decision.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Producing the End Stage Report and updating the Business Case

Managing a Stage Boundary requires the Project Manager to prepare the End Stage Report, update the Business Case, and create the Next Stage Plan so the Project Board can decide whether to continue. Updating the Business Case is the activity that demonstrates continued viability and benefits realisation, giving the Board the assurance it requested. Board authorisation is a separate decision, not an activity of the process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Capturing lessons in the Lessons Log

    Why it's wrong here

    Capturing lessons is an important activity, but it is not the primary mechanism that gives the Project Board assurance that the project remains viable and the stage has delivered. Lessons are recorded throughout the project and reviewed at stage boundaries, yet the viability assurance comes from the updated Business Case and the End Stage Report.

  • ✗

    Producing the Checkpoint Report

    Why it's wrong here

    Checkpoint Reports are produced during the delivery of a stage by the Team Manager to report progress to the Project Manager. They are not part of Managing a Stage Boundary and do not provide the Project Board with the stage-end viability and delivery assurance that the End Stage Report and updated Business Case provide.

  • ✓

    Producing the End Stage Report and updating the Business Case

    Why this is correct

    Within Managing a Stage Boundary, the Project Manager produces the End Stage Report, reviews and updates the Business Case, and prepares the Next Stage Plan. Updating the Business Case provides the Project Board with evidence that the project remains viable and aligned with benefits, which directly supports the assurance the Board is seeking at stage end.

  • ✗

    Authorising the next stage

    Why it's wrong here

    Authorising the next stage is a decision made by the Project Board, not an activity performed by the Project Manager within Managing a Stage Boundary. The Project Manager prepares the information that enables that decision, but the authorisation itself sits with the Board and does not constitute the assurance activity the question describes.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.