PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

A project is midway through the 'Managing a Stage Boundary' process. The Project Manager is reviewing the business case and the next stage plan. The Project Board has not yet approved the next stage. Who is responsible for producing the End Stage Report, and when is it created?

⚠ Common exam trap

The trap here is assuming that the Project Board or Project Assurance produces the End Stage Report, when it is actually the Project Manager's responsibility.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Manager, during the Managing a Stage Boundary process.

The End Stage Report is produced by the Project Manager during the Managing a Stage Boundary process. It provides the Project Board with a summary of stage performance, including progress against the stage plan and business case updates, to support the decision to approve the next stage. This ensures that the Board has the necessary information before authorising the subsequent stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The Project Board, during the Directing a Project process.

    Why it's wrong here

    The Project Board does not produce the End Stage Report; they review it. Their role in Directing a Project is to make key decisions, such as approving the next stage, based on the information provided by the Project Manager. Producing the report is a Project Manager responsibility within the Managing a Stage Boundary process.

  • ✗

    The Project Manager, during the Closing a Project process.

    Why it's wrong here

    The Closing a Project process occurs at the end of the project, not at the end of each stage. The End Stage Report is specifically produced at the end of each management stage (except the final stage, where a project closure report may be used). Therefore, this timing is incorrect for an End Stage Report.

  • ✓

    The Project Manager, during the Managing a Stage Boundary process.

    Why this is correct

    The Project Manager is responsible for producing the End Stage Report as part of the Managing a Stage Boundary process. This report summarises stage performance and is used by the Project Board to decide whether to approve the next stage. It is created before the next stage begins, ensuring that the Board has the necessary information to make an informed decision.

  • ✗

    The Project Assurance role, during the Managing a Stage Boundary process.

    Why it's wrong here

    Project Assurance provides independent oversight and advice, but does not produce the End Stage Report. That is a Project Manager responsibility. Project Assurance may review the report for compliance and viability, but the creation and ownership lie with the Project Manager.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.