Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is in the Controlling a Stage process. The project manager receives a request from a team manager to change the design specification because of a technical difficulty. The change would not affect the stage plan or the business case. What should the project manager do first?

⚠ Common exam trap

The trap here is that candidates often jump to escalation (Option C) or risk management (Option A) without first performing the mandatory step of logging the issue in the Issue Register and assessing its impact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Log the issue in the Issue Register and assess the impact

According to PRINCE2, when a team manager raises a technical difficulty that could result in a change, the project manager must first log it as an issue in the Issue Register. Only after logging and assessing the impact can the project manager decide on the appropriate response. Since the change does not affect the stage plan or business case, the project manager can handle it within the stage without escalating to the project board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Risk Register and create a risk response

    Why it's wrong here

    This is an issue, not a risk, as it has already occurred.

  • Log the issue in the Issue Register and assess the impact

    Why this is correct

    This is the correct initial action for managing issues.

  • Escalate the issue to the project board for a decision

    Why it's wrong here

    Escalation is not needed if the change does not affect tolerances.

  • Instruct the team manager to proceed with the change

    Why it's wrong here

    The change must be formally assessed first.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.