PRINCE2F PRINCE2 Practices Practice Question
A project is in the Closing a Project process. The project manager is preparing the End Project Report. Which TWO of the following should be included in the End Project Report? (Choose two.)
⚠ Common exam trap
The trap here is assuming that the End Project Report contains all project documentation, such as the full Business Case or Risk Register, rather than summarizing key performance data.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
A review of how the project performed against its baselines
The End Project Report includes a review of project performance against baselines and an assessment against tolerances. These elements provide the project board with the necessary information to judge whether the project delivered its objectives and remained within agreed boundaries. Other documents like the Business Case, Risk Register, and stage plans are referenced but not duplicated in full.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
A list of all project risks that were identified during the project
Why it's wrong here
The End Project Report does not include a comprehensive list of all risks; that is the purpose of the Risk Register. The report may summarize key risks and their outcomes, but it does not duplicate the entire Risk Register. Including all risks would make the report unwieldy and redundant.
- ✗
The detailed stage plan for the final stage
Why it's wrong here
The detailed stage plan for the final stage is not included in the End Project Report. Stage plans are working documents used during the project, and the final stage plan would have been used during the final stage. The End Project Report focuses on overall project performance, not on the minutiae of stage plans.
- ✓
A review of how the project performed against its baselines
Why this is correct
The End Project Report includes a review of the project's performance against its baselines (e.g., scope, time, cost, quality). This provides the project board with an assessment of whether the project delivered what was expected. It is a key component for evaluating project success and informing lessons learned.
- ✓
An assessment of the project's performance against its tolerances
Why this is correct
The End Project Report includes an assessment of how the project performed against its tolerances (e.g., time, cost, scope, quality, risk, benefits). This helps the project board determine if the project remained within the agreed boundaries and whether any deviations were justified. It is essential for evaluating overall project success.
- ✗
The project's Business Case with an updated forecast of costs and benefits
Why it's wrong here
While the Business Case is reviewed during Closing a Project, the End Project Report does not contain the full Business Case. Instead, it references the Business Case and may include an assessment of benefits realization. The Business Case itself is a separate document that is updated throughout the project.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.