Courseiva

PRINCE2F Overview of PRINCE2 and Principles Practice Question

A PRINCE2 project to develop a new software system is in the initiation stage. The Project Manager is reviewing the project's approach to controlling changes. The Project Board is concerned that changes to requirements are being made without assessing their impact on the business case. Which PRINCE2 principle is most directly violated if changes are made without such assessment?

⚠ Common exam trap

The trap here is focusing on change control mechanics rather than the principle that requires ongoing validation of the Business Case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Continued business justification

The continued business justification principle mandates that the project remains aligned with its Business Case. Any change must be evaluated for its impact on the Business Case to ensure the project still delivers value. Allowing changes without such assessment undermines this principle, making it the most directly violated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Learn from experience

    Why it's wrong here

    Learn from experience focuses on capturing and applying lessons throughout the project. While changes should consider lessons, the core issue here is that changes are not being evaluated for their impact on the Business Case, which is a matter of continued business justification, not lessons learned.

  • ✓

    Continued business justification

    Why this is correct

    This principle requires that a project has a valid Business Case and that it remains justified throughout. Changes that are not assessed against the Business Case could undermine the project's viability. Therefore, allowing changes without impact assessment directly violates the principle of continued business justification.

  • ✗

    Manage by stages

    Why it's wrong here

    Manage by stages involves dividing the project into manageable stages and controlling each stage. The scenario does not mention stages or stage boundaries; it is about change control and the Business Case. Thus, this principle is not the most directly violated.

  • ✗

    Manage by exception

    Why it's wrong here

    Manage by exception establishes tolerances for delegation. The scenario does not indicate that tolerances are being exceeded or that the Board is not being informed. The key issue is that changes are not assessed for their impact on the Business Case, which relates to continued business justification.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.