Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

A PRINCE2 project is in the process of being set up. The Executive is appointing the project management team. Which role is responsible for ensuring that the project delivers the specified benefits?

⚠ Common exam trap

The trap here is attributing benefits realization to the Senior User, who is concerned with user requirements, rather than the Executive, who owns the business case.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is accountable for the project's business case and ensures that the project delivers the benefits defined in it. While other roles contribute, the Executive holds ultimate responsibility for benefits realization, making them the correct choice. This aligns with PRINCE2's principle of defined roles and responsibilities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents the interests of those who will use the project's products and is responsible for specifying user requirements and ensuring benefits are realized. However, overall accountability for the project delivering benefits lies with the Executive. The Senior User contributes to the business case but does not have ultimate responsibility.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the interests of those designing, developing, and implementing the project's products. They are responsible for the technical integrity of the project and ensuring that supplier resources are available. They do not have primary responsibility for benefits realization, which is a business-focused concern.

  • ✓

    Executive

    Why this is correct

    The Executive is the single point of accountability for the project and is responsible for ensuring that the project delivers the specified benefits. They own the business case and must ensure that the project remains justified throughout. This role represents the business interests and is ultimately answerable for the project's success in realizing benefits.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager is responsible for the day-to-day management of the project, including planning, monitoring, and controlling. They ensure the project delivers the required products within tolerances, but they do not own the benefits. Benefits realization is a higher-level accountability that rests with the Executive and the business organization.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.