MB-920 Describe Dynamics 365 Supply Chain Management Practice Question

Which TWO planning methods are available in Dynamics 365 Supply Chain Management's master planning?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Material requirements planning (MRP)

Options D and E are correct because master planning in Dynamics 365 Supply Chain Management supports both material requirements planning (MRP) and distribution requirements planning (DRP). Option A is incorrect because capacity requirements planning (CRP) is a related but separate process from master planning. Option B is incorrect because enterprise resource planning (ERP) is the system category, not a planning method. Option C is incorrect because production planning is a broader term that encompasses various planning methods, but it is not a specific planning method available in master planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Capacity requirements planning (CRP)

    Why it's wrong here

    CRP is a separate module, not part of master planning.

  • Enterprise resource planning (ERP)

    Why it's wrong here

    ERP is the overall system, not a planning method within master planning.

  • Production planning

    Why it's wrong here

    Production planning is a broader concept, not a specific method in master planning.

  • Material requirements planning (MRP)

    Why this is correct

    MRP calculates material needs for production.

  • Distribution requirements planning (DRP)

    Why this is correct

    DRP plans distribution and replenishment across locations.

About these practice questions

This MB-920 question is part of Courseiva's 930-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on MB-920

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO planning methods are available in Dynamics 365 Supply Chain Management for master planning?

easy
  • A.Coverage planning
  • B.Net change
  • C.Regenerative
  • D.Intercompany planning
  • E.Demand planning

Why B: Options B and C are correct. Net change and regenerative are the two master planning methods in Dynamics 365 Supply Chain Management. Option A (coverage planning) is a type of planning, not a method. Option D (intercompany planning) is a scenario. Option E (demand planning) is a separate module, not a master planning method.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.