MB-920 Describe Dynamics 365 Finance Practice Question
A company uses Dynamics 365 Finance and wants to track budget funds availability before posting purchase orders. Which budget control configuration must be enabled?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Budget control
Budget control must be enabled and configured to check funds availability for purchase orders. Option A is wrong because budget plans are for planning, not control. Option B is wrong because budget register entries record budget amounts, but do not enforce control. Option D is wrong because budget models define the budget structure, not control.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Budget plan
Why it's wrong here
Budget plans are for planning, not control.
- ✗
Budget register entry
Why it's wrong here
Budget register entries record budgets, not control.
- ✓
Budget control
Why this is correct
Budget control enables checking funds availability before purchase orders are posted.
- ✗
Budget model
Why it's wrong here
Budget models are used in budget planning.
Go deeper
Related to this question
About these practice questions
One of 930 original MB-920 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.