MB-910 Describe Dynamics 365 Field Service Practice Question
A field service company uses Dynamics 365 Field Service with Resource Scheduling Optimization (RSO). They notice that RSO is not assigning work orders to technicians who have the required skills, even though those technicians have availability. What is the most likely cause?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The RSO schedule board settings are configured to prioritize other resources based on distance or cost.
Resource Scheduling Optimization (RSO) prioritizes work orders based on configured schedule board settings such as distance, cost, or priority. If these settings favor other resources over the technicians with the required skills, RSO will assign work to those resources first, even if the skilled technicians are available. Option B is incorrect because geofencing is used for location tracking, not for assigning work orders. Option C is incorrect because the problem states that technicians have the required skills, so skill level is not an issue. Option D is incorrect because the technicians' work hours are set correctly, and RSO respects work hours; incorrect hours would cause a different issue.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The RSO schedule board settings are configured to prioritize other resources based on distance or cost.
Why this is correct
RSO uses optimization constraints; technicians may be deprioritized if others are closer or cheaper.
- ✗
Geofencing is enabled and the technicians are outside the service area.
Why it's wrong here
Geofencing is for real-time location alerts, not for blocking RSO assignments.
- ✗
The technicians have not been assigned the correct skill level.
Why it's wrong here
If skills are missing, RSO would not assign; but the scenario states they have the required skills.
- ✗
The technicians' work hours are set incorrectly in their resource record.
Why it's wrong here
Incorrect work hours would prevent assignment, but the scenario says they have availability.
Go deeper
Related to this question
About these practice questions
Courseiva writes every MB-910 question from scratch — 941 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This MB-910 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-910 exam.