Courseiva
ProcesseseasyMultiple ChoiceObjective-mapped

PRINCE2-PRACTITIONER Processes Practice Question

Which PRINCE2 process is responsible for creating the detailed plan for the stage immediately following initiation?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiating a Project

Initiating a Project includes creating the Project Initiation Documentation and the Stage Plan for the first delivery stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating a Project

    Why this is correct

    IP plans the first delivery stage alongside creating the PID.

  • Directing a Project

    Why it's wrong here

    Directing a Project is the board's process.

  • Starting up a Project

    Why it's wrong here

    Starting up a Project only plans the initiation stage itself.

  • Managing a Stage Boundary

    Why it's wrong here

    Stage boundary management plans subsequent stages after the first one.

About these practice questions

One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint

This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.