PRINCE2-PRACTITIONER Processes Practice Question
Which PRINCE2 process is responsible for creating the detailed plan for the stage immediately following initiation?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Initiating a Project
Initiating a Project includes creating the Project Initiation Documentation and the Stage Plan for the first delivery stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiating a Project
Why this is correct
IP plans the first delivery stage alongside creating the PID.
- ✗
Directing a Project
Why it's wrong here
Directing a Project is the board's process.
- ✗
Starting up a Project
Why it's wrong here
Starting up a Project only plans the initiation stage itself.
- ✗
Managing a Stage Boundary
Why it's wrong here
Stage boundary management plans subsequent stages after the first one.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.