When executing the Closing a Project process, who is responsible for confirming handover and acceptance of the project's products?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Customer / User
Handover and acceptance of the project products must be confirmed by the customer or user before final project closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Board Executive
Why it's wrong here
While the Executive authorizes closure, operational acceptance is confirmed by the user/customer.
- ✗
Project Assurance
Why it's wrong here
Project Assurance provides independent check, not operational acceptance.
- ✓
The Customer / User
Why this is correct
The customer or user must formally accept and confirm handover of the project products.
- ✗
Project Manager
Why it's wrong here
The Project Manager facilitates closure activities, but the customer confirms operational acceptance.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.