PRINCE2-PRACTITIONER Practices Practice Question
Under the PRINCE2 Organizing practice, which role represents the interests of those who will use the project's outputs, operate the resulting solution, or realize the benefits?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior User
The Senior User role represents the interests of those who will use the project's outputs or realize benefits.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Senior User
Why this is correct
The Senior User specifies user requirements and monitors for benefit realization.
- ✗
Project Assurance
Why it's wrong here
Project Assurance monitors project performance independently across business, user, and supplier interests.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier represents the interests of those designing, developing, and delivering the project's products.
- ✗
Executive
Why it's wrong here
The Executive is responsible for the overall business justification and viability of the project.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.