In the PRINCE2 Issues practice, what is the primary purpose of a Request for Change?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To formally propose a modification to a project baseline.
A Request for Change is a formal proposal to modify a project baseline (such as scope, products, or plans).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To report a defect in a product that failed its quality review.
Why it's wrong here
That is an off-specification.
- ✗
To request additional risk register entries.
Why it's wrong here
Risks are managed via the Risk practice.
- ✗
To request extra vacation time for the project manager.
Why it's wrong here
HR administrative requests are handled outside project issue control.
- ✓
To formally propose a modification to a project baseline.
Why this is correct
A Request for Change proposes altering established baselines.
About these practice questions
Courseiva writes every PRINCE2-PRACTITIONER question from scratch — 297 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.