Question 220 of 500
Tools and DocumentationhardMultiple ChoiceObjective-mapped

Quick Answer

The answer is the variance analysis report, which is the correct tool for identifying specific work package cost overruns in a project. This report works by comparing the planned budgeted cost of work scheduled against the actual costs incurred at the work package level, calculating key metrics like cost variance (CV = EV - AC) and schedule variance (SV = EV - PV) to isolate exactly where the overrun is occurring. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of the Control Costs process and the distinction between reports that aggregate data versus those that drill down into individual work packages. A common trap is confusing the variance analysis report with a simple status report or a cumulative cost report, which only show totals without isolating the source. Remember the memory tip: "Variance is the pair—CV for cost, SV for schedule—and the work package is where you find the culprit."

PK0-005 Tools and Documentation Practice Question

This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is reviewing the project budget and notices that the actual cost is significantly higher than planned. The project manager wants to identify which specific work packages are causing the overrun. Which report or tool should be used?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Variance analysis report

A variance analysis report compares planned (budgeted) costs against actual costs at the work package level, enabling the project manager to pinpoint specific packages causing the cost overrun. This report directly supports the control costs process by calculating cost variance (CV = EV - AC) and schedule variance (SV = EV - PV) for each work package, isolating the source of the overrun.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Status report

    Why it's wrong here

    Status report gives high-level summary, not detailed variance.

  • Variance analysis report

    Why this is correct

    Variance analysis report compares planned vs actual costs at work package level.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Pareto chart

    Why it's wrong here

    Pareto chart prioritizes issues but does not provide cost variance per work package.

  • Earned value report

    Why it's wrong here

    Earned value report provides overall cost and schedule performance, not detailed per work package.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the distinction between a variance analysis report (which isolates work package-level cost variances) and an earned value report (which shows aggregate EVM metrics), leading candidates to mistakenly choose the earned value report when the question specifically asks for identifying which work packages are causing the overrun.

Detailed technical explanation

How to think about this question

Variance analysis at the work package level uses the earned value management (EVM) formula CV = EV - AC, where a negative CV indicates a cost overrun. The project manager can generate a variance analysis report from the project management information system (PMIS) by filtering on work packages with CV < 0, often expressed as a percentage (CV%) to normalize against budget. In practice, this report may also include to-complete performance index (TCPI) to forecast whether remaining work can be completed within the remaining budget.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Variance analysis report — A variance analysis report compares planned (budgeted) costs against actual costs at the work package level, enabling the project manager to pinpoint specific packages causing the cost overrun. This report directly supports the control costs process by calculating cost variance (CV = EV - AC) and schedule variance (SV = EV - PV) for each work package, isolating the source of the overrun.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.