- A
15 days
Why wrong: 15 is the activity duration, not float.
- B
20 days
Why wrong: 20 is the late finish, not float.
- C
5 days
Total float = late start - early start = 5 days.
- D
10 days
Why wrong: 10 is the difference between late finish and early start, not total float.
Quick Answer
The answer is 5 days. This is correct because total float is calculated by subtracting the early start from the late start, or the early finish from the late finish; here, late start (10) minus early start (5) equals 5 days. Total float represents the amount of time a non-critical activity can be delayed without impacting the project’s overall completion date, making it a key metric for schedule flexibility. On the CompTIA Project+ PK0-005 exam, this concept tests your ability to distinguish between critical and non-critical paths, and a common trap is confusing total float with free float or misapplying the formula to critical path activities, which always have zero float. A reliable memory tip is to think “Late minus Early” for both start and finish—if the result is positive, the activity is non-critical; if zero, it’s on the critical path.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
5 days
Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Here, Late Start (10) minus Early Start (5) equals 5 days. This represents the amount of time the activity can be delayed without affecting the project's overall completion date.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
15 days
Why it's wrong here
15 is the activity duration, not float.
- ✗
20 days
Why it's wrong here
20 is the late finish, not float.
- ✓
5 days
Why this is correct
Total float = late start - early start = 5 days.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
10 days
Why it's wrong here
10 is the difference between late finish and early start, not total float.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is confusing activity duration (Early Finish minus Early Start) or individual dates (Late Start or Late Finish) with the float calculation, leading candidates to pick 15, 20, or 10 days instead of correctly computing the difference.
Detailed technical explanation
How to think about this question
Total float is a critical path method (CPM) metric that applies only to non-critical path activities; critical path activities have zero float. The formula Total Float = Late Start - Early Start (or Late Finish - Early Finish) assumes a forward and backward pass through the network diagram. In real-world construction projects, miscalculating float can lead to improper resource leveling and schedule compression decisions.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: 5 days — Total float is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). Here, Late Start (10) minus Early Start (5) equals 5 days. This represents the amount of time the activity can be delayed without affecting the project's overall completion date.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.