Question 219 of 500
Tools and DocumentationhardMultiple ChoiceObjective-mapped

Quick Answer

The correct conclusion is that the project is behind schedule and under budget. This is determined by interpreting the SPI and CPI in earned value management: an SPI of 0.8, being less than 1.0, means the project has earned only 80% of the value planned for the time spent, indicating a schedule delay; a CPI of 1.1, being greater than 1.0, means the project is earning $1.10 of value for every dollar spent, showing cost efficiency and a budget surplus. On the CompTIA Project+ PK0-005 exam, this question tests your ability to read earned value metrics and avoid the common trap of confusing the two indices—many test-takers mistakenly think a high CPI means a schedule problem. A simple memory tip is to remember that “SPI is for Schedule” (both start with S) and “CPI is for Cost” (both start with C), and that values below 1 are bad (behind or over), while values above 1 are good (ahead or under).

PK0-005 Tools and Documentation Practice Question

This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

An IT project manager is using a project management software tool to track progress. The tool shows that the project's SPI is 0.8 and CPI is 1.1. Which conclusion can the project manager draw about the project's performance?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule and under budget.

The SPI (Schedule Performance Index) of 0.8 indicates that the project is behind schedule, as SPI < 1 means less progress was achieved than planned. The CPI (Cost Performance Index) of 1.1 indicates the project is under budget, as CPI > 1 means the earned value exceeds the actual cost. Therefore, the project is behind schedule and under budget, making option D correct.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is behind schedule and over budget.

    Why it's wrong here

    CPI > 1 means under budget, not over.

  • The project is on schedule and on budget.

    Why it's wrong here

    SPI != 1 and CPI != 1, so not on schedule or budget.

  • The project is ahead of schedule and over budget.

    Why it's wrong here

    SPI < 1 indicates behind schedule, not ahead.

  • The project is behind schedule and under budget.

    Why this is correct

    SPI=0.8 (behind schedule), CPI=1.1 (under budget).

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the direction of the indices, mistakenly thinking CPI > 1 means over budget and SPI < 1 means ahead of schedule, when in fact the opposite is true.

Detailed technical explanation

How to think about this question

SPI is calculated as Earned Value (EV) divided by Planned Value (PV); a value below 1.0 means the project has earned less value than planned for the work scheduled. CPI is EV divided by Actual Cost (AC); a value above 1.0 means the project is earning more value per dollar spent than budgeted. In project management software tools, these indices are recalculated dynamically as tasks are updated, providing real-time performance metrics that inform corrective actions.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is behind schedule and under budget. — The SPI (Schedule Performance Index) of 0.8 indicates that the project is behind schedule, as SPI < 1 means less progress was achieved than planned. The CPI (Cost Performance Index) of 1.1 indicates the project is under budget, as CPI > 1 means the earned value exceeds the actual cost. Therefore, the project is behind schedule and under budget, making option D correct.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.