Question 380 of 500
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is that the project is behind schedule due to Task C. This is correct because Task C has a negative float of -2 days, meaning it is already two days late relative to its latest allowable finish date. Since Task C lies on the critical path—where total float is normally zero—any negative float directly indicates a delay that pushes out the entire project’s completion date. On the CompTIA Project+ PK0-005 exam, this scenario tests your ability to interpret schedule variance by linking negative float on the critical path to overall project status; a common trap is assuming any negative float is acceptable or ignoring that only critical path delays affect the finish date. Remember the memory tip: “Negative float on the critical path equals a late project—no float, no buffer, no excuse.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.

Project Schedule (Gantt Chart) – Excerpt:
Task A: 1/1 - 1/10
Task B: 1/5 - 1/15
Task C (dependent on A and B): 1/16 - 1/25
Task D: 1/20 - 1/25

Current Date: 1/18. Task A and B are 100% complete. Task C has not started. Task D started on schedule.

Refer to the exhibit. The project manager is reviewing the schedule. What is the status of the project?

Question 1mediummultiple choice
Full question →

Exhibit

Refer to the exhibit.

Project Schedule (Gantt Chart) – Excerpt:
Task A: 1/1 - 1/10
Task B: 1/5 - 1/15
Task C (dependent on A and B): 1/16 - 1/25
Task D: 1/20 - 1/25

Current Date: 1/18. Task A and B are 100% complete. Task C has not started. Task D started on schedule.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule due to Task C

Task C has a negative float of -2 days, indicating that it is behind schedule by 2 days. Since Task C is on the critical path (float = 0 in the original schedule), any delay directly extends the project completion date. The project is therefore behind schedule due to Task C.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is slightly ahead of schedule

    Why it's wrong here

    Task C delay offsets any ahead status.

  • The project is on schedule

    Why it's wrong here

    Task C is late.

  • The project is behind schedule due to Task C

    Why this is correct

    Task C should have started but hasn't.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is critically delayed because of Task D

    Why it's wrong here

    Task D started on time.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often assume any task with a delay (like Task D) is the cause of project delay, but only tasks on the critical path with negative float actually delay the project; Task D has positive float and is not critical.

Detailed technical explanation

How to think about this question

Float (or slack) is calculated as Late Start minus Early Start (or Late Finish minus Early Finish). A negative float indicates that the task is already behind schedule and will delay the project end date unless corrective action is taken. In project management, the critical path is the sequence of tasks with zero or negative float; any delay on these tasks directly extends the project duration. Real-world scheduling tools like Microsoft Project or Primavera P6 automatically calculate float and highlight critical paths, making this a key metric for project control.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is behind schedule due to Task C — Task C has a negative float of -2 days, indicating that it is behind schedule by 2 days. Since Task C is on the critical path (float = 0 in the original schedule), any delay directly extends the project completion date. The project is therefore behind schedule due to Task C.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.