- A
Stakeholder register
Correct. The stakeholder register identifies stakeholders and is often created during initiation.
- B
Risk register
Why wrong: Incorrect. The risk register is created during planning.
- C
Project charter
Correct. The project charter is the primary output that authorizes the project.
- D
Lessons learned
Why wrong: Incorrect. Lessons learned are documented throughout the project, especially at closure.
- E
Project schedule
Why wrong: Incorrect. The schedule is developed during planning.
Quick Answer
The answer is the project charter and the stakeholder register. These are the two key outputs of the project initiation phase because the charter formally authorizes the project and gives the project manager authority, while the stakeholder register captures everyone impacted by the project along with their interests and influence. On the CompTIA Project+ PK0-005 exam, this tests your understanding of the Initiating process group, where the focus is on high-level scope definition and early engagement planning. A common trap is confusing the stakeholder register with the communications management plan, which is actually created later during planning. Remember the memory tip: “Charter to start, register for the heart”—the charter kicks off the project, and the register captures the people who care about it.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are outputs of the project initiation phase?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Stakeholder register
The stakeholder register is an output of the project initiation phase because it identifies all individuals or organizations impacted by the project and documents their interests, influence, and expectations. This register is created during initiation to ensure stakeholder engagement strategies are defined early, aligning with PMI's process of identifying stakeholders as part of the Initiating process group.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Stakeholder register
Why this is correct
Correct. The stakeholder register identifies stakeholders and is often created during initiation.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Risk register
Why it's wrong here
Incorrect. The risk register is created during planning.
- ✓
Project charter
Why this is correct
Correct. The project charter is the primary output that authorizes the project.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Lessons learned
Why it's wrong here
Incorrect. Lessons learned are documented throughout the project, especially at closure.
- ✗
Project schedule
Why it's wrong here
Incorrect. The schedule is developed during planning.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between outputs of initiation versus planning, specifically that the risk register and project schedule are planning-phase artifacts, not initiation deliverables, even though they are commonly mistaken as early outputs.
Detailed technical explanation
How to think about this question
The project charter formally authorizes the project and provides the project manager with authority to apply organizational resources, making it a key initiation output. Under the hood, the charter includes high-level requirements, milestones, and budget constraints, and it is often signed by the sponsor or PMO before any detailed planning begins. In real-world scenarios, without a signed charter, project teams risk scope creep and lack of executive support, as the charter serves as the foundational governance document.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Stakeholder register — The stakeholder register is an output of the project initiation phase because it identifies all individuals or organizations impacted by the project and documents their interests, influence, and expectations. This register is created during initiation to ensure stakeholder engagement strategies are defined early, aligning with PMI's process of identifying stakeholders as part of the Initiating process group.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.