Question 410 of 500
Project Management ConceptseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is to add the risk to the risk register and develop a response plan. This is correct because, according to the PMBOK Guide’s risk management process, the next step after risk identification in planning is to formally document the risk in the risk register before any analysis or response planning can occur. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of the sequential flow within the Plan Risk Management and Identify Risks processes; a common trap is jumping straight to mitigation or avoidance without first recording the risk. Remember the memory tip: “Register before Respond”—you cannot manage what you haven’t logged. Once the risk is in the register, the team can analyze its probability and impact, then develop a response plan, ensuring the project stays on track despite the supplier threat.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is assigned to a project that has already been chartered. The project sponsor has provided the project charter and initial budget. The project manager is now in the planning phase. During the first planning meeting, the team identifies a major risk: a key supplier may go out of business before the project ends. The project manager needs to proceed. Which of the following is the NEXT step?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Add the risk to the risk register and develop a response plan.

Option C is correct because the project manager is in the planning phase, and the first step when a risk is identified is to formally document it in the risk register. After adding the risk, the team should analyze it and develop a response plan. This aligns with the PMBOK Guide's risk management process, which requires recording risks before taking action.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately switch to an alternative supplier.

    Why it's wrong here

    This is a drastic action without proper analysis of alternatives.

  • Continue planning and address the risk later.

    Why it's wrong here

    Delaying risk response increases exposure.

  • Add the risk to the risk register and develop a response plan.

    Why this is correct

    Formal risk management begins with documentation and planning.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate the risk to the sponsor for decision.

    Why it's wrong here

    The project manager can handle this risk without escalation.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse immediate action (Option A) with proper risk management, or they think escalation (Option D) is always required for major risks, when in fact the risk register is the correct first step per PMI methodology.

Detailed technical explanation

How to think about this question

In project risk management, the risk register is a living document that captures each risk's description, probability, impact, and planned response. The response plan may include mitigation (e.g., dual-sourcing), transfer (e.g., performance bonds), or acceptance (e.g., contingency reserve). A real-world scenario: if a key cloud service provider faces bankruptcy, the project manager might add a risk response to migrate workloads to a secondary provider, but only after documenting the risk and evaluating alternatives.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Add the risk to the risk register and develop a response plan. — Option C is correct because the project manager is in the planning phase, and the first step when a risk is identified is to formally document it in the risk register. After adding the risk, the team should analyze it and develop a response plan. This aligns with the PMBOK Guide's risk management process, which requires recording risks before taking action.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.