- A
Build the project team
Why wrong: Team building can occur concurrently but is not the immediate next step.
- B
Create a work breakdown structure
Why wrong: WBS is created as part of scope planning, not the first step in detailed planning.
- C
Develop the project management plan
Correct. After charter approval, the project manager develops the comprehensive project management plan.
- D
Conduct risk planning
Why wrong: Risk planning is a sub-plan within the overall plan.
Quick Answer
The answer is to develop the project management plan. This is the correct next step after project charter approval because the charter authorizes the project and provides high-level constraints, but the project management plan is the comprehensive, formal document that defines exactly how the project will be executed, monitored, controlled, and closed. On the CompTIA Project+ PK0-005 exam, this tests your understanding of the PMI planning process sequence, where the project management plan is created before any detailed subsidiary plans like the scope baseline or schedule. A common trap is jumping straight to creating the Work Breakdown Structure (WBS) or building the team, but the plan must come first to establish the approach and baselines. Remember the memory tip: "Charter says go, Plan says how."
PK0-005 Tools and Documentation Practice Question
This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A marketing project manager is responsible for launching a new product. The project manager has created a project charter, a stakeholder register, and a high-level schedule. The sponsor has approved the charter. The project manager needs to develop a detailed project plan. According to best practices, what should the project manager do next?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Develop the project management plan
According to PMI best practices, after the project charter is approved, the next step is to develop the project management plan. This plan defines how the project will be executed, monitored, and controlled, and it serves as the baseline for all subsequent planning activities, including scope, schedule, cost, risk, and quality. The project manager must create this comprehensive plan before building the team or creating detailed deliverables like the WBS.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Build the project team
Why it's wrong here
Team building can occur concurrently but is not the immediate next step.
- ✗
Create a work breakdown structure
Why it's wrong here
WBS is created as part of scope planning, not the first step in detailed planning.
- ✓
Develop the project management plan
Why this is correct
Correct. After charter approval, the project manager develops the comprehensive project management plan.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Conduct risk planning
Why it's wrong here
Risk planning is a sub-plan within the overall plan.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the misconception that creating a WBS or building the team should happen immediately after charter approval, but the correct sequence requires developing the project management plan first to establish the governance and planning framework.
Detailed technical explanation
How to think about this question
The project management plan is a formal, approved document that integrates all subsidiary plans (scope, schedule, cost, quality, risk, communications, etc.) and baselines. Under PMI's PMBOK Guide, the 'Develop Project Management Plan' process is the first process in the Planning Process Group after the Initiating Process Group (which includes charter approval). A real-world scenario: a project manager who jumps to building the team or creating a WBS without an approved plan risks rework, scope creep, and misaligned stakeholder expectations because there is no agreed-upon framework for decision-making.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Tools and Documentation — study guide chapter
Learn the concepts, then practise the questions
- →
Tools and Documentation practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Develop the project management plan — According to PMI best practices, after the project charter is approved, the next step is to develop the project management plan. This plan defines how the project will be executed, monitored, and controlled, and it serves as the baseline for all subsequent planning activities, including scope, schedule, cost, risk, and quality. The project manager must create this comprehensive plan before building the team or creating detailed deliverables like the WBS.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.