Question 376 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is the option where the Cost Performance Index (CPI) is 0.92 and the Schedule Performance Index (SPI) is 0.80, because both values are less than 1.0, which signals the project is over budget and behind schedule. A CPI below 1 means the project is earning less value for every dollar spent, indicating a cost overrun, while an SPI below 1 means the project is progressing slower than planned, indicating a schedule delay. On the CompTIA Project+ PK0-005 exam, interpreting CPI and SPI values tests your ability to quickly assess project health using earned value management; a common trap is confusing values above 1 as good when they actually indicate underperformance for cost and schedule. Remember the memory tip: “Less than one? Under the gun.” — if either index dips below 1.0, that metric is in trouble.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.
Earned Value Report as of Month 3:
PV=$150k, EV=$120k, AC=$130k.

Which statement is true?

Question 1hardmultiple choice
Full question →

Exhibit

Refer to the exhibit.
Earned Value Report as of Month 3:
PV=$150k, EV=$120k, AC=$130k.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Cost Performance Index (CPI) = 0.92, Schedule Performance Index (SPI) = 0.80

Option B is correct because both the Cost Performance Index (CPI) of 0.92 and the Schedule Performance Index (SPI) of 0.80 are less than 1.0, indicating the project is over budget and behind schedule. A CPI below 1 means the project is earning less value for each dollar spent (cost overrun), while an SPI below 1 means the project is progressing slower than planned (schedule delay). This is the only option where both indices are under 1.0, which is a common realistic scenario in troubled projects.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • CPI = 1.08, SPI = 0.8

    Why it's wrong here

    CPI would be >1 if AC were less than EV, not the case.

  • Cost Performance Index (CPI) = 0.92, Schedule Performance Index (SPI) = 0.80

    Why this is correct

    Correct. CPI=120/130=0.92, SPI=120/150=0.80.

    Related concept

    Read the scenario before looking for a memorised answer.

  • CPI = 0.92, SPI = 1.2

    Why it's wrong here

    SPI >1 would require EV>PV, which is not true.

  • CPI = 1.08, SPI = 1.2

    Why it's wrong here

    Both indices are incorrectly high.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the direction of the indices—thinking a value above 1 is always bad—or they fail to recognize that only option B presents a consistent scenario where both cost and schedule performance are unfavorable, which is the most common exam context for EVM interpretation.

Detailed technical explanation

How to think about this question

Earned Value Management (EVM) uses CPI = EV/AC and SPI = EV/PV. A CPI of 0.92 means for every dollar spent, only $0.92 of value is earned, indicating a cost overrun of 8%. An SPI of 0.80 means the project is progressing at 80% of the planned rate, indicating a 20% schedule delay. In real-world projects, these indices are often used together to forecast Estimate at Completion (EAC = BAC/CPI) and to trigger corrective actions; a project with both indices below 1 is typically flagged for immediate management attention.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Cost Performance Index (CPI) = 0.92, Schedule Performance Index (SPI) = 0.80 — Option B is correct because both the Cost Performance Index (CPI) of 0.92 and the Schedule Performance Index (SPI) of 0.80 are less than 1.0, indicating the project is over budget and behind schedule. A CPI below 1 means the project is earning less value for each dollar spent (cost overrun), while an SPI below 1 means the project is progressing slower than planned (schedule delay). This is the only option where both indices are under 1.0, which is a common realistic scenario in troubled projects.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.