Question 285 of 500
Project Management ConceptshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is that the project is over budget and ahead of schedule. This interpretation is correct because the cost performance index (CPI) of 0.8 means the project is earning only $0.80 for every dollar spent, signaling a cost overrun, while the schedule performance index (SPI) of 1.1 indicates it is earning $1.10 for every dollar of planned work, meaning progress is ahead of schedule. On the CompTIA Project+ PK0-005 exam, this question tests your ability to read CPI and SPI values together—a common trap is assuming both indexes must be above 1.0 for a healthy project, but here the mixed values show a trade-off between cost and time. To interpret cost performance index and schedule performance index quickly, remember the mnemonic: “CPI under 1 is cost undone, SPI over 1 is schedule won.”

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is reviewing a project that has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What is the best interpretation?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "best"

    Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and ahead of schedule

A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating cost overrun (over budget). An SPI of 1.1 means the project is earning $1.10 for every $1.00 of planned work, indicating progress ahead of schedule. Therefore, the project is over budget and ahead of schedule, making option B correct.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is on budget and on schedule

    Why it's wrong here

    Both indices deviate from 1.

  • The project is over budget and ahead of schedule

    Why this is correct

    CPI<1 over budget, SPI>1 ahead of schedule.

    Clue confirmation

    The clue word "best" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is over budget and behind schedule

    Why it's wrong here

    SPI 1.1 indicates ahead of schedule.

  • The project is under budget and ahead of schedule

    Why it's wrong here

    CPI 0.8 indicates over budget.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often misinterpret CPI and SPI values, confusing values below 1.0 as 'good' or failing to recognize that a CPI of 0.8 clearly indicates cost overrun regardless of the SPI value.

Detailed technical explanation

How to think about this question

CPI and SPI are earned value management (EVM) metrics derived from actual cost (AC), earned value (EV), and planned value (PV). CPI = EV/AC, so a value below 1.0 means costs are exceeding the value of work performed. SPI = EV/PV, so a value above 1.0 means more work has been completed than planned. In real-world scenarios, this combination often occurs when a project accelerates work by using overtime or additional resources, driving up costs while advancing the schedule.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is over budget and ahead of schedule — A CPI of 0.8 means the project is earning only $0.80 for every $1.00 spent, indicating cost overrun (over budget). An SPI of 1.1 means the project is earning $1.10 for every $1.00 of planned work, indicating progress ahead of schedule. Therefore, the project is over budget and ahead of schedule, making option B correct.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.