Question 471 of 500

Quick Answer

The correct first step is to analyze the critical path and determine if resource addition will help. This is because blindly adding resources to a project that is behind schedule can actually worsen delays due to Brooks’ Law, which states that adding manpower to a late software project makes it later. The critical path contains the sequence of tasks that directly determine the project’s duration, and only tasks on this path can potentially shorten the timeline when resources are added; non-critical tasks already have float, and adding resources to them does nothing for the overall schedule. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of schedule compression techniques and the risks of crashing without analysis—a common trap is assuming more resources always mean faster delivery. A helpful memory tip is “Check the path before you crash,” reminding you to always analyze the critical path before applying crashing or adding resources.

PK0-005 Practice Question: Basics of IT Infrastructure and IT Project Management

This PK0-005 practice question tests your understanding of basics of it infrastructure and it project management. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project to migrate on-premises email to Office 365 is behind schedule. The project sponsor asks the project manager to add more resources to accelerate the timeline. The project manager should first:

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the critical path and determine if resource addition will help

Adding resources to a project that is behind schedule can sometimes worsen the delay due to Brooks' Law, especially if the critical path involves tasks that are not parallelizable. The project manager must first analyze the critical path to determine if adding resources will actually reduce the duration of critical tasks, such as mailbox migration batches or DNS cutover steps, or if it will introduce coordination overhead that negates any gains.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add two additional migration specialists immediately

    Why it's wrong here

    Adding resources without analysis may not improve speed and can increase coordination overhead.

  • Update the project schedule to reflect the new timeline

    Why it's wrong here

    Updating the schedule without addressing the root cause is premature.

  • Analyze the critical path and determine if resource addition will help

    Why this is correct

    Analyzing the critical path shows where compression is possible and if extra resources are beneficial.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Reduce the project scope by deferring non-critical features

    Why it's wrong here

    Scope reduction should be approved through change control, not as a first response.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates assume adding resources always speeds up a project (the 'resource myth'), but Cisco tests the understanding that the critical path must be analyzed first to avoid violating Brooks' Law or hitting infrastructure constraints.

Detailed technical explanation

How to think about this question

In email migration projects, the critical path often includes sequential dependencies such as directory synchronization, mailbox data extraction, and cutover validation. Adding parallel resources to a sequential task (e.g., splitting a single migration batch into multiple parallel batches) can reduce duration only if the underlying infrastructure (e.g., network bandwidth, Exchange throttling limits) supports concurrent migrations without contention. Real-world scenarios often involve Office 365 migration limits (e.g., 150 concurrent migrations per batch) that cap the benefit of adding more specialists.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Basics of IT Infrastructure and IT Project Management — This question tests Basics of IT Infrastructure and IT Project Management — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Analyze the critical path and determine if resource addition will help — Adding resources to a project that is behind schedule can sometimes worsen the delay due to Brooks' Law, especially if the critical path involves tasks that are not parallelizable. The project manager must first analyze the critical path to determine if adding resources will actually reduce the duration of critical tasks, such as mailbox migration batches or DNS cutover steps, or if it will introduce coordination overhead that negates any gains.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PK0-005 practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.