The answer is CV = -$30,000 and SV = -$50,000. This is correct because cost variance (CV) is earned value (EV) minus actual cost (AC), yielding $100,000 minus $130,000, while schedule variance (SV) is EV minus planned value (PV), giving $100,000 minus $150,000. Both negative results indicate the project is over budget and behind schedule, a core concept in earned value management (EVM) tested on the CompTIA Project+ PK0-005 exam. You will often see these calculations in exhibit-based questions where you must pull EV, AC, and PV from a chart or table, and a common trap is confusing which value to subtract—remember that variance always subtracts the baseline (AC for cost, PV for schedule) from EV. To keep it straight, think of the mnemonic “EV comes first, then subtract the other” and note that negative variances mean trouble: cost overrun and schedule delay.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Exhibit
Refer to the exhibit.
```
Project Status Report (Month 3 of 12)
Planned Value (PV): $500,000
Earned Value (EV): $450,000
Actual Cost (AC): $480,000
Budget at Completion (BAC): $2,000,000
```
Refer to the exhibit. What is the cost variance (CV) and schedule variance (SV)?
Refer to the exhibit.
```
Project Status Report (Month 3 of 12)
Planned Value (PV): $500,000
Earned Value (EV): $450,000
Actual Cost (AC): $480,000
Budget at Completion (BAC): $2,000,000
```
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
CV = -$30,000; SV = -$50,000
The cost variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). From the exhibit, EV = $100,000 and AC = $130,000, so CV = $100,000 - $130,000 = -$30,000. The schedule variance (SV) is EV minus Planned Value (PV); with PV = $150,000, SV = $100,000 - $150,000 = -$50,000. Both negative values indicate the project is over budget and behind schedule.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
✓
CV = -$30,000; SV = -$50,000
Why this is correct
Correct calculations.
Related concept
Read the scenario before looking for a memorised answer.
✗
CV = -$20,000; SV = -$20,000
Why it's wrong here
Incorrect.
✗
CV = -$50,000; SV = -$30,000
Why it's wrong here
Swapped.
✗
CV = $30,000; SV = $50,000
Why it's wrong here
Signs reversed.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between cost and schedule variance formulas, and the trap here is confusing which metric uses Actual Cost (AC) versus Planned Value (PV), leading candidates to swap the CV and SV calculations or misread the exhibit values.
Detailed technical explanation
How to think about this question
Earned Value Management (EVM) integrates scope, schedule, and cost data to provide objective performance metrics. CV and SV are fundamental EVM indicators; CV = EV - AC measures cost efficiency (negative means over budget), while SV = EV - PV measures schedule efficiency (negative means behind schedule). In practice, these metrics are used to calculate performance indices (CPI = EV/AC, SPI = EV/PV) and forecast Estimate at Completion (EAC = BAC/CPI), enabling proactive corrective actions.
KKey Concepts to Remember
Read the scenario before looking for a memorised answer.
Find the constraint that changes the correct option.
Eliminate answers that are true in general but not in this case.
TExam Day Tips
→Watch for words such as best, first, most likely and least administrative effort.
→Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: CV = -$30,000; SV = -$50,000 — The cost variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). From the exhibit, EV = $100,000 and AC = $130,000, so CV = $100,000 - $130,000 = -$30,000. The schedule variance (SV) is EV minus Planned Value (PV); with PV = $150,000, SV = $100,000 - $150,000 = -$50,000. Both negative values indicate the project is over budget and behind schedule.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.