- A
Three-point estimating
Why wrong: Used for more refined estimates.
- B
Parametric estimating
Why wrong: Needs statistical relationship and data.
- C
Bottom-up estimating
Why wrong: Requires detailed scope definition.
- D
Analogous estimating
Best for early, high-level estimating.
Quick Answer
The answer is analogous estimating. This technique is the correct choice for early project phases because it relies on historical data from similar past projects to generate a rough order-of-magnitude (ROM) estimate when only a high-level scope is available, requiring no detailed breakdown of work packages. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of how to match estimation methods to project constraints; a common trap is choosing parametric estimating, which demands measurable parameters you lack at this stage. Remember, analogous estimating is your go-to for top-down, quick estimates when information is scarce—think of it as using a “similar project snapshot” to forecast costs. A helpful memory tip: “Analogous = Alike past projects” to anchor the concept.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Compare every option against the stated constraints before choosing — the best answer satisfies all requirements, not just the most obvious one. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is assigned to a new project. The sponsor provides a high-level scope and asks for a cost estimate. Which estimation technique should the project manager use at this early stage?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Analogous estimating
At the early stage of a project when only a high-level scope is available, analogous estimating is the most appropriate technique. It uses historical data from similar past projects to produce a rough order-of-magnitude (ROM) estimate quickly, without requiring detailed breakdowns. This aligns with the PMBOK guide's recommendation for early, top-down estimates when information is limited.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Three-point estimating
Why it's wrong here
Used for more refined estimates.
- ✗
Parametric estimating
Why it's wrong here
Needs statistical relationship and data.
- ✗
Bottom-up estimating
Why it's wrong here
Requires detailed scope definition.
- ✓
Analogous estimating
Why this is correct
Best for early, high-level estimating.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the misconception that parametric estimating is always more accurate than analogous, but at the early stage with high-level scope, parametric lacks the required defined parameters, making analogous the correct choice despite its lower accuracy.
Detailed technical explanation
How to think about this question
Analogous estimating is a top-down technique that leverages historical data from similar projects, adjusting for differences in size, complexity, or inflation. It is often used in the initiation phase to provide a quick, ballpark figure (typically -25% to +75% accuracy) for budget approval. In practice, project managers may combine analogous estimating with expert judgment to refine the estimate when historical data is sparse.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Analogous estimating — At the early stage of a project when only a high-level scope is available, analogous estimating is the most appropriate technique. It uses historical data from similar past projects to produce a rough order-of-magnitude (ROM) estimate quickly, without requiring detailed breakdowns. This aligns with the PMBOK guide's recommendation for early, top-down estimates when information is limited.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.