PK0-005 Tools and Documentation Practice Question
A project team is using Jira for an agile project. The product owner wants to see the total amount of work completed each sprint and the remaining work. Which two charts should the project manager use? (Choose two, but this is a multiple-choice single select for the best pair. Actually, this is a multiple-choice question asking for a single best tool.)
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Burnup and burndown charts
A burnup chart shows completed work over time and total work; a burndown chart shows remaining work. Both together give a complete picture.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Cumulative flow diagram and histogram
Why it's wrong here
Cumulative flow diagram shows work in progress, not specifically completed vs remaining.
- ✗
Gantt chart and milestone chart
Why it's wrong here
Gantt and milestone charts are for traditional scheduling, not sprint work tracking.
- ✓
Burnup and burndown charts
Why this is correct
Correct: Burnup shows completed work and total; burndown shows remaining work.
- ✗
Velocity chart and control chart
Why it's wrong here
Velocity chart shows story points per sprint; control chart shows cycle time, not completed vs remaining.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.