PRINCE2-PRACTITIONER Processes Practice Question
Which TWO of the following roles are actively involved in the Managing Product Delivery (MP) process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
The Project Manager and the Team Manager are the key roles interacting within Managing Product Delivery.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Corporate/Programme management
Why it's wrong here
Corporate operates outside the immediate project management team.
- ✗
Senior Supplier only
Why it's wrong here
Team Managers can be internal or external; the Senior Supplier does not run MP.
- ✓
Team Manager
Why this is correct
The Team Manager executes the MP process.
- ✓
Project Manager
Why this is correct
The Project Manager assigns Work Packages to and receives them from the Team Manager.
- ✗
Executive
Why it's wrong here
The Executive operates within Directing a Project, not day-to-day MP.
About these practice questions
This PRINCE2-PRACTITIONER question is part of Courseiva's 297-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.