Courseiva
← Back to SAFe Product Owner / Product Manager questions

Scenario-based practice

Refer to the Exhibit Practice Questions

Practise SAFe Product Owner / Product Manager practice questions — original exam-style scenarios covering every exam domain, with detailed explanations, wrong-answer analysis, and common exam traps.

15
scenario questions
POPM
exam code
Scaled Agile
vendor

Scenario guide

How to approach refer to the exhibit practice questions

Practise exhibit-style questions that ask you to read a topology, table, command output or diagram before choosing the best answer.

Quick answer

Exhibit-style questions test whether you can read a topology, command output, diagram or table before choosing the best answer.

How to extract the relevant detail from an exhibit.

How topology, command output or routing information affects the answer.

How to avoid answering from memory before reading the evidence.

How to map the exhibit back to the exam objective.

Related practice questions

Related POPM topic practice pages

Scenario questions usually connect to one or more exam topics. Use these links to review the underlying concepts behind the scenario.

Practice set

Practice scenarios

Question 1hardmultiple choice
Full question →

Refer to the exhibit. As a Product Manager preparing for PI Planning, what is your primary concern based on the provided logs?

Exhibit

PROGRAM_CONTEXT_LOG: { 'Architectural_Runway': 'Depleted', 'Capacity_Allocation': 'Enablers 10%', 'Feature_Readiness': 'Low' }
Question 2hardmultiple choice
Full question →

Refer to the exhibit. Given this status report, what is the most critical immediate action for the Product Manager?

Exhibit

{
  "Planning_Readiness": {
    "Vision_Defined": true,
    "Backlog_Ready": false,
    "Architectural_Runway": "Insufficient",
    "Strategic_Themes": "Updated"
  }
}
Question 3hardmultiple choice
Full question →

Refer to the exhibit. Based on the WSJF scores, which feature should be prioritized first for the upcoming PI?

Exhibit

FEATURE_WSJF: { 'ID': 'F1', 'CoD': 5, 'Size': 2, 'Score': 2.5 }, { 'ID': 'F2', 'CoD': 8, 'Size': 8, 'Score': 1.0 }, { 'ID': 'F3', 'CoD': 3, 'Size': 1, 'Score': 3.0 }
Question 4mediummultiple choice
Full question →

Refer to the exhibit. What is the significance of having these criteria met for each feature in the backlog?

Exhibit

{
  "Review_Action": "Validate_Feature_Readiness",
  "Criteria": {
    "Weighted_Shortest_Job_First": "Computed",
    "Acceptance_Criteria": "Defined",
    "Dependencies": "Identified"
  }
}
Question 5hardmultiple choice
Full question →

Given the exhibit, what is the best strategy for the PO to manage the iteration?

Exhibit

PI Objective: Increase API throughput by 20%.
Story A (High Value): Optimize database query (8 story points).
Story B (Low Value): Refactor logging service (3 story points).
Team Velocity: 12 points.
Constraint: Database server upgrade delayed by 2 weeks.
Question 6hardmultiple choice
Full question →

Refer to the exhibit. The team's planned work exceeds capacity by 5 points. What should the Product Owner do before finalizing the plan?

Exhibit

PI_GOAL: Reduce Latency
CURRENT_STORY_POINTS: 40
CAPACITY: 35
TEAM_BUFFER: 5
STATUS: Uncommitted
Question 7mediummultiple choice
Full question →

Refer to the exhibit. What should the Product Owner do?

Exhibit

Team A Velocity: 30. Backlog: 60 points. The team is midway through the iteration. A high-priority emergency defect is reported that will take 10 points to fix.
Question 8mediummultiple choice
Full question →

Refer to the exhibit. As the Product Manager, you have identified PBI-882 as a critical feature for the upcoming PI. However, it shows a dependency on the Architectural Runway. What is your best course of action?

Exhibit

PROGRAM_BACKLOG_ITEM: PBI-882
STATUS: In-Refinement
PRIORITY: High
ESTIMATED_SIZE: 15 Story Points
DEPENDENCY: Arch-Runway-Phase-2
TEAM_ASSIGNMENT: TBD
Question 9hardmultiple choice
Full question →

Refer to the exhibit. Why is 'Feature Z' not suitable for the upcoming PI Planning cycle?

Exhibit

{
  "item": "Feature Z",
  "status": "In Progress",
  "last_update": "30 days ago",
  "priority": "High",
  "definition_of_ready": {
    "acceptance_criteria": "Missing",
    "architectural_review": "Completed"
  }
}
Question 10mediummultiple choice
Full question →

Refer to the exhibit. Given the high number of blockers and low resolution rate, what is the primary responsibility of Leadership during PI Planning to address this?

Exhibit

PROGRAM_BOARD_STATUS: { 'PI_ID': 'Q3-2024', 'TOTAL_DEPENDENCIES': 45, 'BLOCKERS_IDENTIFIED': 12, 'RESOLUTION_RATE': 'LOW', 'LEADERSHIP_INTERVENTION': 'REQUIRED' }
Question 11hardmultiple choice
Full question →

Refer to the exhibit. The 'Payment Gateway' objective is marked as 'Blocked'. As the Product Owner, what is your most appropriate immediate action?

Exhibit

JSON_POLICY: {
  "PI_Objective": "Enhance Payment Gateway",
  "Acceptance_Criteria": "User can pay with Crypto",
  "Priority": "Critical",
  "Status": "Blocked"
}
Question 12mediummultiple choice
Full question →

Refer to the exhibit. What must the Product Manager do immediately following this feedback?

Exhibit

{
  "System_Architect_Feedback": {
    "Enabler_Status": "Critical_Missing",
    "Impact": "High_Risk_To_Delivery"
  }
}
Question 13mediummultiple choice
Full question →

Refer to the exhibit. As a Product Manager, what should you do regarding Feature X?

Exhibit

{
  "policy": "All features in the program backlog must be reviewed by the System Architect for technical viability prior to being marked as 'ready'.",
  "status": "Feature_X has no signature from System Architect."
}
Question 14mediummultiple choice
Full question →

Refer to the exhibit. The ROAMing session has not yet been conducted. What is the leader's next step?

Exhibit

RISK_LOG: [ { 'RISK': 'Dependency on legacy vendor', 'LEVEL': 'High' }, { 'RISK': 'Lack of test environment', 'LEVEL': 'Medium' }, { 'RISK': 'Team turnover', 'LEVEL': 'High' } ]; ROAM_STATUS: { 'RESOLVED': 0, 'OWNED': 0, 'ACCEPTED': 0, 'MITIGATED': 0 };
Question 15hardmultiple choice
Full question →

Refer to the exhibit. How should the PO interpret this drop in velocity for future planning?

Exhibit

Team Velocity (Last 4 iterations): 
I1: 30 
I2: 28 
I3: 32 
I4: 15 
Notes: Team had significant turnover in I4.