This domain covers how SAFe leaders—Product Managers, Business Owners, RTEs, and Scrum Masters—guide PI Planning across both days. Questions test your judgment on handling mid-PI scope changes, running the management review and problem-solving, and coaching teams toward measurable PI Objectives and aligned features.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Leadership for PI Planning

What the exam tests

What to know about Leadership for PI Planning

Recommend deferring new mid-PI features to the Program Backlog for the next PI, keep the committed plan stable, and use Plan Review and problem-solving to surface dependencies. The single most important thing: protect the current PI while capturing new demand transparently.

Business Owner and Product Manager roles in the Day 2 management review and problem-solving session

How to protect the current PI from mid-planning scope changes and route new features correctly

Coaching Product Owners to write specific, measurable PI Objectives tied to business value

Detecting cross-team feature overlap and dependencies and resolving them during draft plan review

Watch out for

Common Leadership for PI Planning exam traps

  • ▸Accepting a Business Owner's mid-PI feature request and inserting it into the current plan instead of the next PI backlog
  • ▸Treating vague PI Objectives as acceptable because they allow flexibility, rather than requiring measurable outcomes
  • ▸Letting teams leave PI Planning with unresolved cross-team dependencies or duplicated features instead of addressing them in problem-solving

Practice set

Leadership for PI Planning questions

20 questions · select your answer, then reveal the explanation

During PI Planning, which THREE of the following represent the responsibilities of Business Owners during the draft plan review? (Choose three)

During PI Planning, a leader notices that a team is not speaking to other teams about their dependencies. What is the best leadership action?

Which TWO actions should a leader take if the 'Program Board' shows a significant, unmitigated dependency?

During PI Planning, a team's Product Owner realizes that a critical feature depends on a component owned by another team that is not present at the event. The dependency was not identified in the Program Board. What is the most appropriate action for the Product Owner to take?

You are a Product Manager for an ART that is about to conduct PI Planning. You want to ensure that the Business Owners are effectively engaged throughout the event. Which two of the following are key responsibilities of Business Owners during PI Planning? (Choose two.)

During the management review and problem-solving session at PI Planning, a Product Manager notices that two teams have conflicting plans for a shared component. The teams are not present in the session. What should the Product Manager do?

An Agile Release Train is conducting its PI Planning event. The Business Owners are present and actively engaged. Which TWO of the following are key responsibilities of the Business Owners during PI Planning? (Choose two.)

During PI Planning, a Business Owner expresses concern that the proposed PI Objectives do not align with the strategic intent for the next quarter. What is the most effective leadership action to resolve this?

Which TWO of the following leadership behaviors effectively support the PI Planning process? (Choose two)

Refer to the exhibit. Given the high number of blockers and low resolution rate, what is the primary responsibility of Leadership during PI Planning to address this?

Exhibit

PROGRAM_BOARD_STATUS: { 'PI_ID': 'Q3-2024', 'TOTAL_DEPENDENCIES': 45, 'BLOCKERS_IDENTIFIED': 12, 'RESOLUTION_RATE': 'LOW', 'LEADERSHIP_INTERVENTION': 'REQUIRED' }

A team has identified a major dependency on an external supplier that is not committed to the PI plan. How should the Release Train Engineer (RTE) or leader address this?

What is the main goal of the Management Review and Problem Solving session during PI Planning?

A Business Owner is consistently pushing teams to commit to more features than their calculated capacity allows. What is the best way to handle this situation?

Refer to the exhibit. Although Total Capacity equals Total Demand, the team-level distribution is skewed. What should leadership do?

Exhibit

TEAM_CAPACITY: { 'TEAM_A': 40, 'TEAM_B': 30, 'TEAM_C': 50 }; FEATURE_DEMAND: { 'FEATURE_X': 45, 'FEATURE_Y': 35, 'FEATURE_Z': 40 }; TOTAL_CAPACITY: 120; TOTAL_DEMAND: 120;

What is the primary role of the Chief Scrum Master or Release Train Engineer (RTE) during the PI Planning process?

Why should leaders encourage the use of the 'Confidence Vote' at the end of PI Planning?

What is the most appropriate action for a leader if a team expresses low confidence during the vote?

Which THREE of the following are key responsibilities of leadership during the PI Planning 'Final Plan Review'?

Refer to the exhibit. The ROAMing session has not yet been conducted. What is the leader's next step?

Exhibit

RISK_LOG: [ { 'RISK': 'Dependency on legacy vendor', 'LEVEL': 'High' }, { 'RISK': 'Lack of test environment', 'LEVEL': 'Medium' }, { 'RISK': 'Team turnover', 'LEVEL': 'High' } ]; ROAM_STATUS: { 'RESOLVED': 0, 'OWNED': 0, 'ACCEPTED': 0, 'MITIGATED': 0 };

During the first day of PI Planning, the Product Manager notices that the team is struggling to estimate stories due to vague requirements. What is the most effective leadership action?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Leadership for PI Planning sessions

Start a Leadership for PI Planning only practice session

Every question in these sessions is drawn from the Leadership for PI Planning domain — nothing else.

Related practice questions

Related POPM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the POPM exam test about Leadership for PI Planning?
Recommend deferring new mid-PI features to the Program Backlog for the next PI, keep the committed plan stable, and use Plan Review and problem-solving to surface dependencies. The single most important thing: protect the current PI while capturing new demand transparently.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Leadership for PI Planning questions in a focused session?
Yes — the session launcher on this page draws every question from the Leadership for PI Planning domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other POPM topics?
Use the topic links above to move to related areas, or go back to the POPM question bank to see all topics.