Refer to the exhibit. The Product Owner must select features for the next iteration. Which combination of features maximizes business value if Feature C has the highest priority and Feature A has the second highest?
Exhibit
Team capacity: 40 points. Feature A: 15 points. Feature B: 15 points. Feature C: 20 points. Feature D: 10 points. Feature E: 5 points.
Trap 1: Features C, B, and D.
This combination includes lower priority features while excluding the second-highest priority item, Feature A. By ignoring the established priority, the team ends up delivering less business value in the iteration. This is a suboptimal decision that fails to align with the product strategy and the PO's goal of maximizing value.
Trap 2: Features A, B, and C.
The total points for this combination (15+15+20) is 50, which exceeds the team's capacity of 40 points. Planning more work than capacity leads to failure in meeting the Sprint Goal, which destroys trust and reduces the team's predictability. The PO must respect capacity constraints to ensure the team can succeed.
Trap 3: Features D, E, B, and A.
This selection excludes the highest priority feature, C, which is the most critical item. Even though the points add up to 40, the lack of priority alignment means the team is not delivering the most valuable outcomes. The PO has failed to prioritize based on business value, resulting in poor economic performance.
- A
Features C, A, and E.
This selection includes the top priority features C and A, then fills the remaining capacity with E. This adheres to the priority order while maximizing the team's capacity of 40 points. It is the most effective use of the team's time to deliver the highest possible value to the business.
- B
Features C, B, and D.
Why it fails: This combination includes lower priority features while excluding the second-highest priority item, Feature A. By ignoring the established priority, the team ends up delivering less business value in the iteration. This is a suboptimal decision that fails to align with the product strategy and the PO's goal of maximizing value.
- C
Features A, B, and C.
Why it fails: The total points for this combination (15+15+20) is 50, which exceeds the team's capacity of 40 points. Planning more work than capacity leads to failure in meeting the Sprint Goal, which destroys trust and reduces the team's predictability. The PO must respect capacity constraints to ensure the team can succeed.
- D
Features D, E, B, and A.
Why it fails: This selection excludes the highest priority feature, C, which is the most critical item. Even though the points add up to 40, the lack of priority alignment means the team is not delivering the most valuable outcomes. The PO has failed to prioritize based on business value, resulting in poor economic performance.