Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project is in the execution phase. An executive stakeholder has been directly assigning tasks to team members without going through you. Several team members are confused about priorities. What should you do FIRST?

⚠ Common exam trap

Many exam-takers choose to escalate immediately (Option C) or try to work around the stakeholder (Option B), failing to recognize that the PMBOK Guide emphasizes resolving issues through direct communication with the stakeholder first, as the project manager is responsible for managing stakeholder expectations and the communication plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Speak with the stakeholder privately to explain the impact of bypassing the PM and reinforce the communication plan

The correct first step is to speak privately with the stakeholder to explain the impact of bypassing the project manager and reinforce the established communication plan. This aligns with the PMBOK Guide's principle of managing stakeholder engagement through direct, respectful communication to resolve issues at the lowest appropriate level before escalating. By addressing the root cause—the stakeholder's lack of awareness or disregard for the communication protocol—you can restore clarity on priorities without prematurely escalating or undermining the stakeholder's relationship.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the stakeholder engagement plan to reduce the stakeholder's influence

    Why it's wrong here

    Reducing influence without communication is not appropriate; the stakeholder may have valid concerns.

  • Ignore the issue and try to align the team's priorities yourself

    Why it's wrong here

    Ignoring the issue will likely worsen confusion and undermine the PM's authority.

  • Inform the sponsor about the stakeholder's behavior

    Why it's wrong here

    Escalation should be a last resort after direct communication fails.

  • Speak with the stakeholder privately to explain the impact of bypassing the PM and reinforce the communication plan

    Why this is correct

    Direct, respectful communication is the best way to resolve the issue and realign expectations.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.