Courseiva

PMP Process — Managing Technical Aspects Practice Question

Your project is in the execution phase. An executive stakeholder has been directly assigning tasks to team members without going through you. Several team members are confused about priorities. What should you do FIRST?

⚠ Common exam trap

Many exam-takers choose to escalate immediately (Option C) or try to work around the stakeholder (Option B), failing to recognize that the PMBOK Guide emphasizes resolving issues through direct communication with the stakeholder first, as the project manager is responsible for managing stakeholder expectations and the communication plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Speak with the stakeholder privately to explain the impact of bypassing the PM and reinforce the communication plan

The correct first step is to speak privately with the stakeholder to explain the impact of bypassing the project manager and reinforce the established communication plan. This aligns with the PMBOK Guide's principle of managing stakeholder engagement through direct, respectful communication to resolve issues at the lowest appropriate level before escalating. By addressing the root cause—the stakeholder's lack of awareness or disregard for the communication protocol—you can restore clarity on priorities without prematurely escalating or undermining the stakeholder's relationship.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Update the stakeholder engagement plan to reduce the stakeholder's influence

    Why it's wrong here

    Editing the engagement plan to curb an executive's influence does not resolve the immediate priority confusion and exceeds the project manager's authority over a senior stakeholder. It tempts because the engagement plan does record stakeholder management approaches, but it is a planning artefact, not the first action for an active conflict.

  • ✗

    Ignore the issue and try to align the team's priorities yourself

    Why it's wrong here

    Ignoring the behaviour leaves the stakeholder assigning work unchecked, so the priority confusion persists and the project manager loses control of the schedule. It tempts because quietly realigning tasks avoids confrontation, but ignoring an active conflict violates the project manager's responsibility to address it directly and promptly.

  • ✗

    Inform the sponsor about the stakeholder's behavior

    Why it's wrong here

    Escalating to the sponsor before addressing the stakeholder directly skips the confrontation and relationship work the project manager owns, and the sponsor is not the first line for resolving resource-assignment conflicts. It tempts because escalation feels decisive, yet it is reserved for when direct engagement fails or authority is genuinely exceeded.

  • ✓

    Speak with the stakeholder privately to explain the impact of bypassing the PM and reinforce the communication plan

    Why this is correct

    Directly addressing the stakeholder preserves the relationship while surfacing the priority confusion their bypassing created. Reinforcing the communication plan restores the PM's coordination role, which is the PM's responsibility during execution before escalating or involving the sponsor.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 820 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.