Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are managing a software upgrade project. During a team meeting, two senior developers get into a heated argument over the best technical approach for a critical component. The disagreement is delaying progress. As the project manager, what should you do FIRST?

⚠ Common exam trap

It's easy for candidates to assume the project manager should either avoid involvement (Option B) or assert authority (Option D), but the PMP exam emphasizes that the project manager's role is to facilitate collaborative conflict resolution, not to dictate technical decisions or escalate prematurely.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting with both developers to reach a consensus

As the project manager, your first responsibility is to facilitate conflict resolution among team members to keep the project on track. By mediating a meeting between the two senior developers, you encourage collaborative decision-making, leverage their technical expertise, and maintain team cohesion without imposing a top-down solution that could damage morale or overlook critical technical nuances.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Facilitate a meeting with both developers to reach a consensus

    Why this is correct

    Facilitating a meeting with both developers to reach a consensus is the most effective approach for a Project Manager. This strategy directly addresses the conflict by encouraging open communication and collaborative problem-solving, allowing the team members to take ownership of the solution. The PM acts as a neutral party, guiding the discussion to ensure a mutually agreeable resolution that maintains team cohesion and commitment to the project's objectives, rather than imposing a potentially resented decision.

  • Allow them to resolve the conflict on their own without intervention

    Why it's wrong here

    Allowing developers to resolve a conflict on their own without intervention is inappropriate when the disagreement is actively delaying project progress. A Project Manager has a responsibility to proactively identify and remove impediments to ensure the project stays on schedule and within scope. Unaddressed conflicts can escalate, leading to prolonged delays, decreased productivity, and potential damage to team morale, necessitating timely PM intervention to mitigate these risks.

  • Escalate the issue to the functional managers of the developers

    Why it's wrong here

    Escalating the issue directly to functional managers should be considered a last resort, not an initial response to a team conflict. The Project Manager's primary role includes directly resolving team-level issues and empowering the project team to find solutions. Premature escalation undermines the PM's authority, can demotivate team members by bypassing their autonomy, and may strain relationships between project and functional management, indicating a failure to manage internal team dynamics effectively.

  • Decide on the approach yourself and assign tasks accordingly

    Why it's wrong here

    Deciding on the approach yourself and assigning tasks accordingly, while seemingly efficient, often fails to resolve the underlying conflict and can be counterproductive. Imposing a solution without team member input can lead to a lack of buy-in, resentment, and demotivation, as the developers may not feel their perspectives were valued or understood. This approach risks superficial compliance rather than genuine commitment, potentially causing the conflict to resurface or manifest in other forms, negatively impacting project quality and team morale.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.