Courseiva
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

Protecting the Team from Ad-Hoc Stakeholder Requests: Work with Product Owner to Establish a Process

During a sprint retrospective, the team expresses frustration that they are frequently interrupted by ad-hoc requests from stakeholders. Scrum Master role you are also the PM. What should you do FIRST?

Quick Answer

The correct answer is to work with the product owner to establish a process for handling ad-hoc requests and shield the team. This is the first action because, as both Scrum Master and PM, your core responsibility is to protect the team from disruptions while still addressing stakeholder needs, which aligns with the servant-leader principle. By collaborating with the Product Owner to create a formal triage and prioritization process, you ensure non-critical requests are deferred to the product backlog rather than derailing the sprint. On the PMP exam, this scenario tests your understanding of stakeholder engagement and the Scrum Master’s role in maintaining team focus, often appearing as a trap where candidates mistakenly jump to coaching stakeholders directly or escalating to management. The key is to remember that the Product Owner owns the backlog, so you must work through them to filter requests. Memory tip: “PO for the flow, SM for the shield”—the Product Owner manages the request flow, while the Scrum Master shields the team.

⚠ Common exam trap

PMI often tests the misconception that a PM should directly control stakeholder requests or add buffers, rather than empowering the Product Owner to manage the backlog and the Scrum Master to shield the team.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work with the product owner to establish a process for handling ad-hoc requests and shield the team

As both Scrum Master and PM, your primary responsibility is to protect the team from disruptions while ensuring stakeholder needs are addressed. Working with the Product Owner to establish a formal process for handling ad-hoc requests—such as triaging, prioritizing, and deferring non-critical items—preserves the team's focus and sprint commitment. This aligns with the servant-leader role of a Scrum Master and the PM's duty to manage stakeholder expectations without bypassing the product backlog.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask stakeholders to submit all requests as change requests for formal approval

    Why it's wrong here

    While change control is formal, it may be too heavy for small ad-hoc requests; a lighter process may be needed.

  • Instruct the team to ignore all ad-hoc requests until the next sprint planning

    Why it's wrong here

    Ignoring stakeholders can damage relationships; better to manage expectations.

  • Add a buffer to the sprint backlog to account for interruptions

    Why it's wrong here

    This normalizes interruptions rather than reducing them, and may violate sprint commitments.

  • Work with the product owner to establish a process for handling ad-hoc requests and shield the team

    Why this is correct

    The product owner can act as a buffer; establishing a clear process reduces disruptions.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a sprint retrospective, the team expresses frustration that they are frequently interrupted by unplanned support requests from the operations department. The product owner agrees this is impacting velocity. What should the project manager do FIRST?

medium
  • A.Work with the product owner to prioritize support requests and allocate a dedicated buffer for them.
  • B.Escalate the issue to the project sponsor to negotiate with operations.
  • C.Ask the team to track the time spent on support requests and report it at the next retrospective.
  • D.Instruct the team to handle support requests as they come to maintain stakeholder satisfaction.

Why A: The immediate priority is to manage the unplanned work that is disrupting the sprint. By working with the product owner to prioritize support requests and allocate a dedicated buffer (e.g., a fixed capacity within the sprint backlog), the project manager ensures that the team can handle operational interruptions without derailing planned work. This aligns with the Agile principle of protecting the team's focus and using empirical data to adjust the process, rather than escalating or deferring action.

Variation 2. During a sprint retrospective, the team expresses frustration that they are frequently interrupted by unplanned work from other departments. The project manager wants to improve team focus. What should the project manager do?

easy
  • A.Increase the sprint duration to accommodate unplanned work
  • B.Tell the team to ignore unplanned work requests
  • C.Add a daily stand-up to discuss unplanned work
  • D.Meet with other department managers to negotiate dedicated team time and establish a process for handling requests

Why D: It addresses the root cause of the team's frustration by negotiating dedicated team time with other departments and establishing a formal process for handling unplanned work requests. This aligns with the servant leadership approach in the People domain, where the project manager acts as a buffer and facilitator to protect the team's focus and productivity, rather than imposing a technical fix that ignores the systemic issue.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.