PMP Practice Question: Business Environment: strategy and project benefits
In a Scrum project, the development team consistently misses deadlines. The project manager (who also serves as the Scrum Master) discovers that the team is overcommitting during sprint planning due to pressure from the product owner. What should the project manager do first?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Coach the product owner on the importance of sustainable pace and realistic commitments.
The project manager, acting as Scrum Master, should first coach the product owner on the importance of sustainable pace and realistic commitments. This addresses the root cause of overcommitment due to pressure, fostering a healthy sprint planning process. Option A bypasses collaboration, undermining the product owner's role. Option B is a superficial capacity fix that doesn't address the planning behavior. Option C escalates prematurely before attempting direct coaching, which is the Scrum Master's primary responsibility.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reduce the sprint backlog to a manageable size without consulting the product owner.
Why it's wrong here
Unilaterally reducing the Sprint Backlog without consulting the Product Owner directly violates Scrum's principle of collaboration and disrespects the Product Owner's accountability for maximizing product value. This action bypasses the critical dialogue needed to understand the Product Owner's priorities and the rationale behind the commitments. Furthermore, it fails to address the underlying behavioral issue of overcommitment, merely treating a symptom rather than fostering a sustainable solution through shared understanding and agreement.
- ✗
Add more team members to increase capacity.
Why it's wrong here
Adding more team members is a superficial solution that fails to address the fundamental issue of unrealistic commitment during Sprint Planning. This approach, often referred to as "Brooks's Law," can actually decrease productivity in the short term due to increased communication overhead, onboarding new members, and the formation of new team dynamics. It avoids coaching the Product Owner on sustainable pace and realistic goal-setting, which is the true root cause of the development team consistently missing commitments.
- ✗
Escalate to senior management about the product owner's behavior.
Why it's wrong here
Escalating directly to senior management is a premature and often counterproductive step for a Scrum Master. The Scrum Master's primary responsibility is to serve the Product Owner and the Development Team by coaching them on Scrum principles and practices, including realistic commitment and sustainable pace. Bypassing direct coaching attempts undermines the Scrum Master's role as a servant leader and impediment remover, potentially damaging team trust and internal relationships before attempting a resolution at the team level.
- ✓
Coach the product owner on the importance of sustainable pace and realistic commitments.
Why this is correct
Coaching the Product Owner on sustainable pace and realistic commitments is the most appropriate and effective action for a Scrum Master. This directly addresses the root cause of the development team consistently missing commitments, which often stems from pressure to deliver more than is feasible. The Scrum Master, as a servant leader, facilitates understanding of empirical process control and helps the Product Owner appreciate the team's actual capacity, fostering a more predictable and healthy development rhythm aligned with core Scrum principles.
Go deeper
Related to this question
Learn chapter
Introduction to the PMP Exam and Project Management Basics
Key term
Sprint Planning
Sprint Planning is a time-boxed meeting at the start of a Scrum sprint where the team decides what work they can deliver and how they will do it.
Key term
Scrum Methodology
Scrum is a lightweight process framework that helps teams deliver complex projects in small, iterative chunks called sprints.
About these practice questions
This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.