Courseiva
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

During project execution, a team member reports that a critical path activity is delayed by two days because a required component failed quality inspection. The project has no schedule contingency. What is the BEST course of action for the project manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Evaluate schedule compression techniques such as crashing or fast tracking to recover the two days

Delaying a critical path activity threatens the project end date. The project manager should first evaluate schedule compression techniques like crashing (adding resources) or fast tracking (performing activities in parallel) to recover the two-day delay without automatically changing scope, baseline, or escalating. Option A (reduce scope) requires a change request and may not be necessary if compression works. Option B (update baseline) is premature; baseline changes should only occur after recovery options are exhausted. Option C (escalate to sponsor and request budget) is an overreaction; escalating for budget before trying compression is not best practice.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reduce the scope of the next deliverable to compensate for the lost time

    Why it's wrong here

    Scope reduction requires change control and is not the first action.

  • Update the schedule baseline to reflect the delay and inform stakeholders

    Why it's wrong here

    Updating the baseline without attempting to recover the delay is not proactive.

  • Escalate the issue to the sponsor and request additional budget for overtime

    Why it's wrong here

    Escalation should come after attempting internal solutions.

  • Evaluate schedule compression techniques such as crashing or fast tracking to recover the two days

    Why this is correct

    The PM should first see if the delay can be recovered using schedule compression techniques.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.