- A
Instruct the team member to follow the executive's order to maintain good relations.
Why wrong: This undermines the PM's authority and risks scope creep and resource overload.
- B
Escalate the issue to the sponsor and request intervention.
Why wrong: Escalation should be a last resort; the PM should first attempt to resolve the issue through direct communication.
- C
Speak with the executive stakeholder privately to explain the change control process and the impact of the request.
The PM should address the issue directly with the stakeholder, reinforcing the need to follow formal processes.
- D
Update the issue log and continue with the original plan.
Why wrong: Ignoring the situation does not address the stakeholder's action and may lead to further issues.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During a project, an executive stakeholder bypasses the project manager and directly instructs a team member to add a new feature. The team member is already overloaded. What should the project manager do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Speak with the executive stakeholder privately to explain the change control process and the impact of the request.
Option C is correct because the project manager must first address the unauthorized change directly with the executive stakeholder, explaining the formal change control process and the impact on scope, schedule, and resources. This aligns with the PMBOK Guide's principle of managing stakeholder expectations and protecting the project from uncontrolled scope creep, which is a key technical aspect of project integration management.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Instruct the team member to follow the executive's order to maintain good relations.
Why it's wrong here
This undermines the PM's authority and risks scope creep and resource overload.
- ✗
Escalate the issue to the sponsor and request intervention.
Why it's wrong here
Escalation should be a last resort; the PM should first attempt to resolve the issue through direct communication.
- ✓
Speak with the executive stakeholder privately to explain the change control process and the impact of the request.
Why this is correct
The PM should address the issue directly with the stakeholder, reinforcing the need to follow formal processes.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Update the issue log and continue with the original plan.
Why it's wrong here
Ignoring the situation does not address the stakeholder's action and may lead to further issues.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may choose Option B (escalation) because they think the executive's authority requires immediate higher-level intervention, but the PMP exam emphasizes that the project manager should first attempt to resolve the issue directly with the stakeholder using communication and process explanation before escalating.
Trap categories for this question
Scenario analysis trap
Ignoring the situation does not address the stakeholder's action and may lead to further issues.
Detailed technical explanation
How to think about this question
In project management, the change control process is governed by the change management plan, which defines how changes to baselines (scope, schedule, cost) are submitted, evaluated, and approved. The project manager acts as the gatekeeper, ensuring that any change request follows the defined workflow, including impact analysis and approval by the change control board (CCB) if required. A real-world scenario where this matters is when an executive stakeholder requests a new software feature mid-sprint; the project manager must first discuss the request privately, document the impact on the sprint backlog and release timeline, and then formally process it through the change control system to avoid disrupting the team's velocity and commitments.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Speak with the executive stakeholder privately to explain the change control process and the impact of the request. — Option C is correct because the project manager must first address the unauthorized change directly with the executive stakeholder, explaining the formal change control process and the impact on scope, schedule, and resources. This aligns with the PMBOK Guide's principle of managing stakeholder expectations and protecting the project from uncontrolled scope creep, which is a key technical aspect of project integration management.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.