Program Stakeholder EngagementmediumMultiple SelectObjective-mapped

PgMP Program Stakeholder Engagement Practice Question

Which THREE communication channels can a program manager use for stakeholder engagement?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Electronic mailing lists.

Multiple channels are required to reach diverse stakeholders effectively.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Public news media.

    Why it's wrong here

    Usually not appropriate for internal program communication.

  • Electronic mailing lists.

    Why this is correct

    Efficient for broad updates.

  • Face-to-face meetings.

    Why this is correct

    High-impact for complex issues.

  • Project portals.

    Why this is correct

    Useful for centralized access to documentation.

  • Social media feeds.

    Why it's wrong here

    Generally too informal for professional program communication.

About these practice questions

Courseiva writes every PgMP question from scratch — 197 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.