PgMP Program Benefits Management Practice Question
A program is entering its sustainment phase. Who is ultimately accountable for ensuring that the benefits continue to be realized after the program team disbands?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Benefits Owner
While the program team hands over the capability, the business operational owners maintain accountability for ongoing benefit sustainment.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Program Manager
Why it's wrong here
The program manager is responsible for the transition, not post-closure sustainment.
- ✓
Benefits Owner
Why this is correct
The Benefits Owner is responsible for the ongoing realization and sustainability of the benefit.
- ✗
Program Sponsor
Why it's wrong here
The sponsor provides high-level support but does not manage day-to-day operations.
- ✗
Project Manager
Why it's wrong here
Project managers are focused on outputs, not long-term business outcomes.
About these practice questions
One of 197 original PgMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.