Which TWO of the following are key elements of a requirements management plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change control process for requirements

The requirements management plan includes the traceability matrix and the change control process to manage requirements throughout the project. System design documents, test cases, and user stories are outputs or artifacts, not elements of the plan itself.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Change control process for requirements

    Why this is correct

    Change control is a key part of managing requirements.

  • Requirements traceability matrix template

    Why this is correct

    The plan defines how traceability will be managed.

  • User stories

    Why it's wrong here

    User stories are a format for requirements, not a plan element.

  • System design documents

    Why it's wrong here

    Design documents are outputs of the design phase.

  • Test cases

    Why it's wrong here

    Test cases are part of testing, not the requirements management plan.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are outputs of the requirements management process?

medium
  • A.Solution design specification
  • B.Project scope statement
  • C.Requirements management plan
  • D.Requirements traceability matrix
  • E.Business case

Why C: The requirements management process produces the requirements management plan and the requirements traceability matrix as its key outputs. The requirements management plan defines how requirements will be collected, analyzed, documented, and managed throughout the project, while the requirements traceability matrix links each requirement to its origin, design, testing, and delivery. These are the formal outputs specified in the PMBOK Guide for the Collect Requirements process.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.