PMI-ACP Product Practice Question

A team has high velocity but the customer reports the product is not meeting their needs. What is the most likely cause?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The product backlog is not prioritized based on customer value.

High velocity is irrelevant if the team is building the wrong things.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The product backlog is not prioritized based on customer value.

    Why this is correct

    The product owner is likely prioritizing technical tasks or low-value features over customer needs.

  • The sprint duration is too short.

    Why it's wrong here

    Sprint length does not inherently determine product value.

  • The team is lacking a project manager.

    Why it's wrong here

    Agile teams focus on self-organization, not the presence of a PM.

  • The team is not using enough automated tests.

    Why it's wrong here

    Quality is important, but product value is the primary concern here.

About these practice questions

One of 218 original PMI-ACP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-ACP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-ACP exam.