You are the project manager of a PRINCE2 project to organize a major industry conference. The executive has asked you to prepare the business case for the project. Which of the following must be included in the business case according to PRINCE2?

⚠ Common exam trap

The trap here is assuming that organizational details or detailed plans are part of the business case, when they are separate documents within the project initiation documentation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Reasons why the project is needed, expected benefits, and associated risks

According to PRINCE2, the business case must include the reasons why the project is needed, the expected benefits, and the associated risks. It also includes costs, timescales, and an investment appraisal. These elements collectively justify the project and ensure it remains desirable, viable, and achievable. The business case is a living document, updated at stage boundaries and in exception situations.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The project's risk management approach and risk register

    Why it's wrong here

    The risk management approach and risk register are separate documents within the project initiation documentation. The business case includes a summary of key risks, but it does not contain the full risk management approach or the detailed risk register. The business case references risks that could affect the business justification, but the comprehensive risk documentation is maintained separately.

  • ✓

    Reasons why the project is needed, expected benefits, and associated risks

    Why this is correct

    The business case in PRINCE2 must include the reasons why the project is needed, the expected benefits, and the associated risks. It also covers costs, timescales, and the investment appraisal. These elements together justify the project and demonstrate that it is desirable, viable, and achievable. This is essential for the project board to make informed decisions about continuing the project.

  • ✗

    The detailed stage plan for the first delivery stage

    Why it's wrong here

    The detailed stage plan is a separate document, typically created by the project manager and approved by the project board. While the stage plan may inform the business case's cost and timescale estimates, it is not a required component of the business case itself. The business case focuses on the overall justification and viability of the project, not the granular planning of a specific stage.

  • ✗

    The project's organization structure and role descriptions

    Why it's wrong here

    The organization structure and role descriptions are part of the project initiation documentation, specifically the organization section, but they are not a required component of the business case itself. The business case focuses on the justification for the project, including benefits, costs, risks, and timescales. While the organization is important for delivery, it is not a core element of the business case.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.