Which TWO documents are produced during the Closing a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Lessons Report

The End Project Report and the Lessons Report are both produced in CP. The Project Brief is from SU, the PID from IP, and the Stage Plan from SB.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Brief

    Why it's wrong here

    The Project Brief is produced in SU.

  • Lessons Report

    Why this is correct

    Correct: The Lessons Report is produced in CP.

  • Stage Plan

    Why it's wrong here

    Stage Plans are produced in SB or IP.

  • End Project Report

    Why this is correct

    Correct: The End Project Report is a key output of CP.

  • Project Initiation Documentation (PID)

    Why it's wrong here

    The PID is produced in IP.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are outputs of the Closing a Project process?

medium
  • A.Business Case
  • B.Project Plan
  • C.End Project Report
  • D.Stage Plan
  • E.Lessons Report

Why C: Closing a Project produces the End Project Report and the Lessons Report.

Variation 2. Which TWO of the following are outputs of the Closing a Project process?

medium
  • A.Lessons Report
  • B.Updated Project Plan
  • C.Updated Business Case
  • D.Stage Plan for the next stage
  • E.End Project Report

Why A: CP produces the End Project Report, Lessons Report, and project closure recommendation. The Project Plan is updated in SB, and the Business Case is updated throughout.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.