Which register is used to record all issues that are raised during the project?

⚠ Common exam trap

PRINCE2F often tests the confusion between the Issue Register and the Risk Register, with candidates incorrectly selecting Risk Register when asked about recording all issues.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Issue Register

The Issue Register is used to record all issues raised during a project. In PRINCE2, issues include Requests for Change, Off-specifications, and general problems or concerns. The Issue Register is maintained by the Project Manager and captures details, actions, and status of each issue.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Risk Register

    Why it's wrong here

    The Risk Register holds uncertainties and their responses, not issues that have already occurred. It is tempting because risks and issues share similar assessment fields and owners, and would be correct when logging a potential future threat rather than a current problem requiring resolution.

  • ✗

    Quality Register

    Why it's wrong here

    The Quality Register records quality activities, tests and their results, not project issues. It is tempting because quality records also capture problems and follow-up actions, and would be correct when documenting planned quality checks and their outcomes rather than issues needing management action.

  • ✗

    Configuration Item Records

    Why it's wrong here

    Configuration Item Records track products, components and their versions and status, not the issues raised against them. It is tempting because configuration management does capture change and status information, and would be correct when recording the composition and version baseline of a delivered product.

  • ✓

    Issue Register

    Why this is correct

    The Issue Register captures every issue raised during the project, recording details, severity, priority, and status for each. PRINCE2 mandates it as the central log satisfying the stem's requirement to record all issues, unlike the Risk Register, which handles uncertainties rather than problems already occurring.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.