Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

Which process is used by the Project Board to authorise the start of a new stage?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

Directing a Project includes authorising stage plans (including exception plans) and project closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why this is correct

    The Project Board authorises stage plans in DP.

  • Initiating a Project

    Why it's wrong here

    IP establishes the project, not subsequent stages.

  • Controlling a Stage

    Why it's wrong here

    CS is PM's process for managing a stage.

  • Managing a Stage Boundary

    Why it's wrong here

    SB prepares the request for the next stage, but authorisation is done by the Project Board in DP.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.