Which process is the Project Board primarily responsible for, according to PRINCE2?
⚠ Common exam trap
Test-takers frequently confuse the Project Board's strategic oversight with the Project Manager's operational responsibilities, leading them to select 'Controlling a Stage' or 'Managing a Stage Boundary' because they involve decision-making, but those are executed by the Project Manager, not the Board.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Project Board is primarily responsible for the 'Directing a Project' process, which covers the overall management and decision-making from project initiation through closure. This process includes authorizing the project, providing key decisions, and ensuring that the project remains viable and aligned with business objectives. The Board does not execute day-to-day management or delivery tasks, which belong to other roles.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.