PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

Which PRINCE2 principle emphasizes that a project must remain viable throughout its lifecycle?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Continued business justification

The 'Continued business justification' principle requires that the Business Case is reviewed and updated regularly to ensure the project remains desirable, viable, and achievable.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Manage by stages

    Why it's wrong here

    Manage by stages divides the project into controllable chunks with decision points, addressing governance and control rather than viability. The continued business justification principle requires a valid Business Case throughout, so it is the one demanding ongoing viability; manage by stages would be chosen when structuring delivery.

  • ✗

    Learn from experience

    Why it's wrong here

    Learn from experience covers capturing and applying lessons throughout the project, not maintaining viability. Continued business justification is the principle requiring a valid Business Case at all times; learn from experience would be the answer if the question concerned reviews, lessons logs or avoiding repeated mistakes.

  • ✓

    Continued business justification

    Why this is correct

    Continued business justification requires a valid Business Case to exist throughout, and the project must be stopped or re-scoped if justification lapses. This directly satisfies the stem's constraint that viability must persist across the entire lifecycle, not merely at initiation.

  • ✗

    Tailor to suit the project environment

    Why it's wrong here

    Tailoring adapts PRINCE2's themes, processes and roles to a project's scale, complexity and environment; it does not address viability. The 'continued business justification' principle requires the Business Case to be reviewed and confirmed viable throughout. Tailoring is tempting because it genuinely shapes how the method is applied, but it governs method fit, not ongoing justification.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.