PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

The Project Manager of a PRINCE2 project is reviewing a Work Package that has been agreed with a Team Manager. During delivery, the Team Manager identifies that a product will cost significantly more than the tolerance allowed in the Work Package. What should the Team Manager do FIRST?

⚠ Common exam trap

The trap here is assuming the Team Manager should escalate straight to the Project Board, when the Work Package defines escalation to the Project Manager first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Immediately inform the Project Manager of the forecast deviation

Within Managing Product Delivery, the Team Manager delivers the Work Package within agreed tolerances. If a forecast breach occurs, the Team Manager must escalate to the Project Manager, who manages the stage and decides whether the deviation exceeds stage tolerance and warrants an Exception Report to the Project Board. Bypassing the Project Manager or silently absorbing costs violates the agreed escalation route.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Continue delivery and absorb the additional cost within the Team Manager's own budget

    Why it's wrong here

    Work Package tolerances are set deliberately and cannot be unilaterally absorbed. Continuing without informing the Project Manager hides a forecast breach and undermines the 'manage by exception' principle. The Team Manager must escalate the forecast deviation so the Project Manager can assess the impact on stage tolerance and take corrective action if necessary.

  • ✗

    Raise an Exception Report directly to the Project Board

    Why it's wrong here

    The Team Manager has no direct reporting line to the Project Board; communication flows through the Project Manager. Raising an Exception Report to the Board bypasses the agreed escalation route and the Project Manager's authority to manage the stage. The Team Manager must first inform the Project Manager, who then decides whether the deviation exceeds stage tolerance and requires escalation.

  • ✓

    Immediately inform the Project Manager of the forecast deviation

    Why this is correct

    The Team Manager is accountable for delivering the Work Package within its tolerances. When a forecast breach is identified, the correct first action is to inform the Project Manager, who can assess the impact against stage tolerances and decide on corrective action. This preserves the escalation path defined in the Work Package and aligns with PRINCE2's manage-by-exception principle.

  • ✗

    Request a formal change to the project's Business Case before proceeding

    Why it's wrong here

    The Business Case is owned by the Executive and updated at stage boundaries, not by a Team Manager during delivery. A cost deviation in a Work Package is first a tolerance issue, not automatically a Business Case change. The Project Manager must assess the deviation before any change or Business Case update is considered.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.